# 光甘草定中试项目实施预算
|
|
|
|
|
|
|
|
|
|
|
|
| 项目 | 内容 |
|
|
|
|
|
|
| --- | --- |
|
|
|
|
|
|
| 文档编号 | GGCD-CB-001 |
|
|
|
|
|
|
| 版本 | V1.0 |
|
|
|
|
|
|
| 币种 | 人民币(万元) |
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
## 1. 阶段一:最小可生产条件
|
|
|
|
|
|
|
|
|
|
|
|
### 1.1 工艺设备(罐体类)
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 位号 | 罐体/柱 | 重量预估(kg) | 预估预算价格 |
|
|
|
|
|
|
| --- | --- | --- | --- |
|
|
|
|
|
|
| U-02 | 50 L 种子罐 | 60 | 2.96 |
|
|
|
|
|
|
| U-01 | 1000 L 发酵罐 | 350 | 8.40 |
|
2026-09-15 11:54:41 +08:00
|
|
|
|
| U-03 | 补料罐 300 L | 120 | 3.92 |
|
|
|
|
|
|
| U-04 | 诱导剂罐 50 L | 40 | 2.64 |
|
|
|
|
|
|
| U-05 | 碱罐 50 L | 35 | 2.56 |
|
|
|
|
|
|
| U-06 | 酸罐 30 L | 30 | 2.48 |
|
|
|
|
|
|
| U-07 | 消泡剂罐 30 L | 30 | 2.48 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| D-31 | 大孔树脂柱 Φ250×1800 | 90 | 3.44 |
|
2026-09-15 11:54:41 +08:00
|
|
|
|
| D-41 | 硅胶柱 Φ300×1200 | 110 | 3.76 |
|
|
|
|
|
|
| D-42 | 结晶罐 100 L | 60 | 2.96 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| **小计** | | | **35.60** |
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
### 1.2 工艺设备(非罐体)
|
|
|
|
|
|
|
|
|
|
|
|
| 位号 | 设备 | 预估预算价格 |
|
|
|
|
|
|
| --- | --- | --- |
|
|
|
|
|
|
| U-20B | 洁净操作台(苏净) | 3 |
|
|
|
|
|
|
| U-20A | 生物安全柜(力康/博科) | 6 |
|
|
|
|
|
|
| U-20S1/S2 | 恒温摇床(2 台,上海智城/知楚) | 6 |
|
2026-09-15 11:54:41 +08:00
|
|
|
|
| D-01 | 高压均质机(上海东华) | 20 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| D-02 | 碟式离心机(赛德力 DBS540) | 50 |
|
|
|
|
|
|
| D-11 | 单罐搅拌批次萃取装置 | 12 |
|
|
|
|
|
|
| D-21 | 刮板薄膜蒸发器(江南药化) | 15 |
|
2026-09-15 11:54:41 +08:00
|
|
|
|
| D-43 | 真空干燥箱 | 3 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| S-01 | 溶剂回收精馏撬 | 35 |
|
|
|
|
|
|
| **小计** | | **150** |
|
|
|
|
|
|
|
|
|
|
|
|
### 1.3 溶剂与公用配套
|
|
|
|
|
|
|
|
|
|
|
|
| 位号 | 设备 | 预估预算价格 |
|
2026-09-15 11:45:56 +08:00
|
|
|
|
| --- | --- | --- |
|
2026-09-15 11:54:41 +08:00
|
|
|
|
| D-12、D-13 | 萃取溶剂储罐(2 台,配套 D-11) | 16.80 |
|
|
|
|
|
|
| D-32、D-33 | 洗脱溶剂储罐(2 台,配套 D-31) | 16.80 |
|
|
|
|
|
|
| D-34 | 石油醚储罐(配套 D-41) | 5.52 |
|
|
|
|
|
|
| C-01 | CIP 站 | 8 |
|
|
|
|
|
|
| C-02 | 电蒸汽发生器(供 SIP) | 6 |
|
|
|
|
|
|
| P-01、P-02 | 活塞式空压机(2 台,含冷干机,捷豹) | 3 |
|
|
|
|
|
|
| P-03 | 除菌过滤器(科百特) | 2 |
|
|
|
|
|
|
| **小计** | | **58.12** |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
|
|
|
|
|
|
### 1.4 公用工程与自控
|
|
|
|
|
|
|
|
|
|
|
|
| 项目 | 预估预算价格 |
|
|
|
|
|
|
| --- | --- |
|
|
|
|
|
|
| 供配电(就近变压器) | 10 |
|
|
|
|
|
|
| 空调箱(AHU) | 8 |
|
|
|
|
|
|
| 控制系统(PLC+上位机+工控机+服务器) | 35 |
|
|
|
|
|
|
| 在线仪表 | 20 |
|
2026-09-15 11:54:41 +08:00
|
|
|
|
| **小计** | **73** |
|
|
|
|
|
|
|
|
|
|
|
|
> 无外部蒸汽接入,SIP 由 C-02 电蒸汽发生器供汽。
|
2026-09-15 11:50:51 +08:00
|
|
|
|
|
|
|
|
|
|
### 1.5 集装箱车间工程
|
|
|
|
|
|
|
|
|
|
|
|
| 项目 | 预估预算价格 |
|
|
|
|
|
|
| --- | --- |
|
|
|
|
|
|
| 车间集装箱(8 个 × 2 万/个) | 16 |
|
2026-09-15 11:56:01 +08:00
|
|
|
|
| 设备房集装箱(2 个 × 2 万/个) | 4 |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| 更衣换鞋与洁净准备集装箱(1 个 × 2 万/个) | 2 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 洁净彩钢板装修(8 个) | 24 |
|
|
|
|
|
|
| 集装箱保温与施工(含模块连接) | 18 |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| **小计** | **64** |
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
2026-09-15 11:58:06 +08:00
|
|
|
|
**阶段一合计:380.7 万元**
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
## 2. 阶段二:污水与环境设备设施
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 项目 | 预估预算价格 |
|
|
|
|
|
|
| --- | --- |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| 滚塑罐(若干,交替使用,外包处理) | 3 |
|
|
|
|
|
|
| 污水处理设备(集装箱式,3 m³,进水 COD 10000) | 50 |
|
|
|
|
|
|
| 废气/VOC 系统(E-01) | 15 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 给排水(清污分流) | 10 |
|
|
|
|
|
|
| 废弃物暂存间 | 5 |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| **阶段二合计** | **83** |
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
## 3. 阶段三:公共工程与化验
|
2026-09-15 11:45:56 +08:00
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 功能间/设施 | 预估预算价格 |
|
|
|
|
|
|
| --- | --- |
|
|
|
|
|
|
| 原料库 | 8 |
|
|
|
|
|
|
| 成品库 | 8 |
|
|
|
|
|
|
| 溶剂库(危化品库) | 10 |
|
|
|
|
|
|
| 包材库 | 8 |
|
|
|
|
|
|
| 质检/微生物实验室 | 15 |
|
|
|
|
|
|
| 纯水间 | 10 |
|
|
|
|
|
|
| 空压站 | 8 |
|
|
|
|
|
|
| 制冷机房 | 10 |
|
|
|
|
|
|
| 配电间 | 10 |
|
|
|
|
|
|
| 蒸汽间/锅炉房 | 8 |
|
|
|
|
|
|
| CIP/SIP 间 | 8 |
|
|
|
|
|
|
| 更衣/缓冲间 | 6 |
|
|
|
|
|
|
| 办公/值班室 | 8 |
|
|
|
|
|
|
| 消防设施 | 15 |
|
|
|
|
|
|
| 通风/排风系统 | 10 |
|
2026-09-15 11:56:01 +08:00
|
|
|
|
| **阶段三合计** | **142** |
|
2026-09-15 11:32:24 +08:00
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
## 4. 安装工程费
|
2026-09-15 11:32:24 +08:00
|
|
|
|
|
2026-09-15 11:58:06 +08:00
|
|
|
|
设备购置费(工艺 185.60 + 溶剂与公用配套 58.12 + 自控 55 + 污水设备 68)× 15% = **55.0**
|
2026-09-15 11:32:24 +08:00
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
## 5. 其他费用
|
2026-09-15 11:32:24 +08:00
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 项目 | 预估预算价格 |
|
2026-09-15 11:32:24 +08:00
|
|
|
|
| --- | --- |
|
|
|
|
|
|
| 压力容器认证 | 15 |
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
## 6. 汇总
|
2026-09-15 11:32:24 +08:00
|
|
|
|
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 阶段 | 金额(万元) |
|
|
|
|
|
|
| --- | --- |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| 阶段一 最小可生产条件 | 380.7 |
|
|
|
|
|
|
| 阶段二 污水与环境设备设施 | 83 |
|
2026-09-15 11:56:01 +08:00
|
|
|
|
| 阶段三 公共工程与化验 | 142 |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| 安装工程费 | 55.0 |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
| 其他(压力容器认证) | 15 |
|
2026-09-15 11:58:06 +08:00
|
|
|
|
| **项目总预算(初估)** | **约 676(取整约 680)** |
|
2026-09-15 11:50:51 +08:00
|
|
|
|
|
2026-09-15 11:58:06 +08:00
|
|
|
|
> 估算精度 ±30%(约 470–880 万元);不含土地、税费、设计费、环评、安评及运营流动资金;远程监控、数据采集与数字孪生为自建,不列入预算。
|